Getting AroundSunday, November 8
Twin Bridges repairs are scheduled to start Monday, with a full southbound closure planned Friday night
The 5AM Henderson team
If you cross the Ohio River on U.S. 41, repairs on the Twin Bridges' southbound span are scheduled to start Monday. The Kentucky Transportation Cabinet is scheduled to begin the work and expects it to run all week. Crews will replace damaged rocker bearings and repair a structural support beam.
The aim is to reopen all four lanes well before Thanksgiving. 14news.com reported Oct. 28 that materials were still being fabricated, and the schedule depended on confirming deliveries.
Twin Bridges repairs run from Monday into Friday night
- Nov. 9Crews are scheduled to begin repairs on the southbound bridge.
- Nov. 11-12Southbound traffic is expected to switch from the left lane to the right lane.
- Nov. 13The southbound bridge will close fully, and all river traffic will use the northbound bridge.
- NovemberKYTC aims to reopen all four lanes much sooner than Thanksgiving.
Sources: The Hendersonian, 14news.com
- Work site: mostly below the bridge
- Current setup: one southbound lane runs on the northbound bridge
- Friday night lanes: one 15-foot lane each way
- Delays: possible while the northbound bridge is restriped
Heading across the river Friday night? We suggest leaving extra time, since the southbound bridge will be fully closed and all river traffic will use the northbound bridge.
The northbound bridge drops to one lane each way Friday night
| Now | Measure | Friday night |
|---|---|---|
| 2 | Northbound lanes | 1 |
| 1 | Southbound lanes | 1 |
Sources: The Hendersonian, 14news.com